Initial Scrunity Report/Observations of Project   - DELHI DEVELOPMENT AUTHORITY,
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: Construction of Commonwealth Games Village Near Akshardhama Temple off Road No.NH-24/SH: C/O internal removable RCC Wall.
2 EXECUTOR/CONTRACTOR/VENDORS: M/s K.R. Anand
3 Project Incharge/Employees Er. K.G. Gupta
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Stadium
  5. Workcode No
  6. Approval Year
  7. State/District/Place
  8. Date of Admin Approval
  9. Administrative Approval Amount
  10. Estimated Cost
  11. Date of Preparation of Estimate
  12. Modes of Tender
  13. Etendering
  14. No of Tenders
  15. Quote of L1 Bidder
  16. Justify Amount
  17. Date of Preparation of Justification
  18. Awarded Contract
  19. Agreement Date
  20. Letter of Intent No
  21. Letter of Intent Date
  22. Work Order No
  23. Agreement No
  24. Vendor/Executor Name
  25. Date of Start As Per Agreement
  26. Actual Date of Start
  27. Date of Completion As Per Agreement
  28. Actual Date of Completion
  29. Stipulate Agreement Time
  30. Physical Progress of Work in Percentage
  31. Financial Progress of Work in Percentage
  32. Manual Adopted
  33. Tender Complaint
  34. No. of Consultants
  35. Name of Consultant
35 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Contractor
  4. Contractor Name
  5. Open Tender
  6. Prequalification As per bidding document
  7. Actual Prequalification Bid Date
  8. Technical bid As Per bidding Document
  9. Actual Technical Bid Date
  10. Financial bid As Per bidding Document
  11. Actual Financial Bid Date
  12. No. of disqualified Bids at Prequalification
  13. No. of disqualified Bids at Technical
  14. No. of Financial Bids Opened
  15. Work Order Date
  16. Payment Made Till Date
  17. No. of Complaint/s
17 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-10-07-2010
Actual Date of Completion-30-08-2010
Not completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:28601134
b. at award stage in % Awarded Cost:49717450
c. at completion stage in % Payment Amount:43093529.00
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           00-00-0000                          00-00-0000 Data Insufficient
iii) Commercial Stage           00-00-0000                          00-00-0000 Data Insufficient
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:20-08-2009
Letter Of Intent Date:20-08-2009
Delayed by 28 days
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 5
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-49717450
Estimated Cost-28601134
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-11-10-2009
Actual Date of Start-11-10-2009
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 11-10-2009
Actual Date of Completion: 30-08-2010
Stipulated Completion Time As Per Agreement: 273
323 days
c. The cost of extra/Deduction/ additional items are more in %. -
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-30-08-2010
Progress of Work-11-06-2011
Delayed by 285 Days


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 1 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 14 0
Scan - Bills 10 9
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0