Initial Scrunity Report/Observations of Project   - DELHI DEVELOPMENT AUTHORITY,
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: D/o CWG Village for Commonwealth Games 2010/ S.H: C/o Noise Barrier (Flyover Side)
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Construction Catalysers Pvt. Ltd.
3 Project Incharge/Employees Er.A.K.Suneja
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Workcode No
  5. Approval Year
  6. State/District/Place
  7. Date of Admin Approval
  8. Administrative Approval Amount
  9. Estimated Cost
  10. Date of Preparation of Estimate
  11. Modes of Tender
  12. Etendering
  13. Prequalification As per bidding document
  14. Actual Prequalification Bid Date
  15. Financial bid As Per bidding Document
  16. Actual Financial Bid Date
  17. No of Tenders
  18. No. of Financial Bids Opened
  19. Justify Amount
  20. Date of Preparation of Justification
  21. Awarded Contract
  22. Letter of Intent No
  23. Letter of Intent Date
  24. Work Order No
  25. Agreement No
  26. Vendor/Executor Name
  27. Date of Start As Per Agreement
  28. Actual Date of Start
  29. Date of Completion As Per Agreement
  30. Actual Date of Completion
  31. Stipulate Agreement Time
  32. Physical Progress of Work in Percentage
  33. Financial Progress of Work in Percentage
  34. Manual Adopted
  35. Tender Complaint
  36. No. of Consultants
  37. Name of Consultant
37 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Stadium
  4. Contractor
  5. Contractor Name
  6. Open Tender
  7. Technical bid As Per bidding Document
  8. Actual Technical Bid Date
  9. No. of disqualified Bids at Prequalification
  10. No. of disqualified Bids at Technical
  11. Quote of L1 Bidder
  12. Agreement Date
  13. Work Order Date
  14. Payment Made Till Date
  15. No. of Complaint/s
15 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-03-09-2010
Actual Date of Completion-03-09-2010
Completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:304
b. at award stage in % Awarded Cost:29992375
c. at completion stage in % Payment Amount:19875176
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           19-02-2010                          19-02-2010 Data Insufficient
ii)Technical Stage           00-00-0000                          00-00-0000 Data Insufficient
iii) Commercial Stage           24-02-2010                          24-02-2010 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:08-03-2010
Letter Of Intent Date:08-03-2010
Delayed by 42 days
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 1
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-29992375
Estimated Cost-304
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-04-05-2010
Actual Date of Start-04-05-2010
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 04-05-2010
Actual Date of Completion: 03-09-2010
Stipulated Completion Time As Per Agreement: 120
122 days
c. The cost of extra/Deduction/ additional items are more in %. 1
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-66
Not Matching
b. Delay in making payments
Actual Date of Completion-03-09-2010
Progress of Work-14-06-2011
Delayed by 284 Days


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 1 1
Scan - Stake Holder Info 1 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 1 1
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0