| Initial Scrunity Report/Observations of Project - CENTRAL PUBLIC WORKS DEPARTMENT |
| Sl.No |
Information Name |
Informations |
System Remarks |
| 1 |
Name of the Project/Work: |
Upgradation and renovation of Dr SPM Swimming Pool Complex for CWG 2010 at Talkatora New Delhi SH Construction of new insulated metal sheet roof along with supporting structure and its integration with existing structure including E&M works |
|
| 2 |
EXECUTOR/CONTRACTOR/VENDORS: |
Ahluwalia Contracts India Limited |
|
| 3 |
Project Incharge/Employees |
Sh V K Dhiman |
|
| 4 |
Completed Project Information: |
-
Officer Incharge
-
Name of Work
-
Organization Name
-
Stadium
-
Workcode No
-
State/District/Place
-
Date of Admin Approval
-
Administrative Approval Amount
-
Estimated Cost
-
Date of Preparation of Estimate
-
Modes of Tender
-
Etendering
-
Prequalification As per bidding document
-
Actual Prequalification Bid Date
-
Technical bid As Per bidding Document
-
Actual Technical Bid Date
-
Financial bid As Per bidding Document
-
Actual Financial Bid Date
-
No of Tenders
-
No. of Financial Bids Opened
-
Quote of L1 Bidder
-
Justify Amount
-
Date of Preparation of Justification
-
Awarded Contract
-
Agreement Date
-
Letter of Intent No
-
Letter of Intent Date
-
Agreement No
-
Vendor/Executor Name
-
Date of Start As Per Agreement
-
Actual Date of Start
-
Date of Completion As Per Agreement
-
Actual Date of Completion
-
Stipulate Agreement Time
-
Physical Progress of Work in Percentage
-
Financial Progress of Work in Percentage
-
Manual Adopted
-
Tender Complaint
-
No. of Consultants
-
Name of Consultant
|
40 Fields are Filled |
| 5 |
Incomplete Project Information- |
-
Major Department
-
Project Category
-
Contractor
-
Contractor Name
-
Approval Year
-
Open Tender
-
No. of disqualified Bids at Prequalification
-
No. of disqualified Bids at Technical
-
Work Order No
-
Work Order Date
-
Payment Made Till Date
-
No. of Complaint/s
|
12 Fields are Empty |
| 6 |
This project is completed/not completed in time. |
Agrrement Date of Completion-16-06-2009 Actual Date of Completion-31-08-2010 |
Not completed on time |
| 7 |
The project exceeds the budget allocation |
|
|
|
a. at estimate stage in % |
Estimated Cost:244905349 |
|
|
b. at award stage in % |
Awarded Cost:287300000 |
|
|
c. at completion stage in % |
Payment Amount:288454383.28 |
|
| 8 |
Tender Processing |
|
|
|
a. Delay in opening of tender |
As Per Agreement
As Per Actual
|
|
|
i)Pre-qualification stage |
23-07-2007
23-07-2007
|
Data Insufficient |
|
ii)Technical Stage |
14-12-2007
14-12-2007
|
Data Insufficient |
|
iii) Commercial Stage |
14-12-2007
14-12-2007
|
No Delay
|
|
b. Very long time taken for the finalization of tender. |
Date Of Preparation of Justify Amount:17-12-2007
Letter Of Intent Date:17-12-2007
|
Delayed by 28 days
|
|
c. Work awarded on nomination basis. |
OpenTender |
|
|
d. Participation of bidder is too low. |
5 |
|
|
e. Work awarded at higher rates in respect to estimated cost.
|
Awarded Cost-287300000 Estimated Cost-244905349 |
Yes |
| 9 |
Execution Stage
|
|
|
|
a. The work was started late. |
Agreement Date of Start-17-01-2008 Actual Date of Start-17-01-2008 |
No Delay
|
|
b. Time taken for completion of work is beyond the stipulated date of completion. |
Actual Date of Start: 17-01-2008Actual Date of Completion: 31-08-2010
Stipulated Completion Time As Per Agreement: 17 Months
|
957 days
|
|
c. The cost of extra/Deduction/ additional items are more in %. |
No |
|
| 10 |
Payments |
|
|
|
a. The physical progress is not matching with the financial progress. |
Work in Percentage-100 Financial Progress Work Percentage-100 |
Matching |
|
b. Delay in making payments
|
Actual Date of Completion-31-08-2010Progress of Work-01-12-2011 |
Delayed by 457 Days |