Initial Scrunity Report/Observations of Project   - CENTRAL PUBLIC WORKS DEPARTMENT
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: SITC of UPS System at Wrestling and Velodrome Stadium
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Power House
3 Project Incharge/Employees Sunil Yadav, EE(E), CGED-II, CPWD, IGI Stadium, Ne
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Workcode No
  5. State/District/Place
  6. Administrative Approval Amount
  7. Estimated Cost
  8. Modes of Tender
  9. Etendering
  10. No of Tenders
  11. No. of Financial Bids Opened
  12. Quote of L1 Bidder
  13. Awarded Contract
  14. Letter of Intent No
  15. Letter of Intent Date
  16. Work Order No
  17. Agreement No
  18. Vendor/Executor Name
  19. Date of Start As Per Agreement
  20. Actual Date of Start
  21. Date of Completion As Per Agreement
  22. Actual Date of Completion
  23. Stipulate Agreement Time
  24. Physical Progress of Work in Percentage
  25. Financial Progress of Work in Percentage
  26. Manual Adopted
  27. Tender Complaint
27 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Stadium
  4. Contractor
  5. Contractor Name
  6. Approval Year
  7. Date of Admin Approval
  8. Date of Preparation of Estimate
  9. Open Tender
  10. Prequalification As per bidding document
  11. Actual Prequalification Bid Date
  12. Technical bid As Per bidding Document
  13. Actual Technical Bid Date
  14. Financial bid As Per bidding Document
  15. Actual Financial Bid Date
  16. No. of disqualified Bids at Prequalification
  17. No. of disqualified Bids at Technical
  18. Justify Amount
  19. Date of Preparation of Justification
  20. Agreement Date
  21. Work Order Date
  22. Payment Made Till Date
  23. No. of Complaint/s
  24. No. of Consultants
  25. Name of Consultant
25 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-18-09-2010
Actual Date of Completion-18-09-2010
Completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:33877646
b. at award stage in % Awarded Cost:34533450
c. at completion stage in % Payment Amount:34528493
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           00-00-0000                          00-00-0000 Data Insufficient
iii) Commercial Stage           00-00-0000                          00-00-0000 Data Insufficient
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 5
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-34533450
Estimated Cost-33877646
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-05-08-2010
Actual Date of Start-05-08-2010
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 05-08-2010
Actual Date of Completion: 18-09-2010
Stipulated Completion Time As Per Agreement: 45 Days
44 days
c. The cost of extra/Deduction/ additional items are more in %. NIL
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-18-09-2010
Progress of Work-18-09-2010
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 0 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 0 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0