| Initial Scrunity Report/Observations of Project - DELHI DEVELOPMENT AUTHORITY, |
| Sl.No |
Information Name |
Informations |
System Remarks |
| 1 |
Name of the Project/Work: |
C/O CWG Village for Commonwealth Games Delhi-2010 Near Akshardham Temple off Road No.NH-24/SH:C/O Swimming Pool Training Hall & Fitness Centre at Commonwealth Games Village - Balance work. |
|
| 2 |
EXECUTOR/CONTRACTOR/VENDORS: |
Sam (India) Built Well Pvt. Ltd. |
|
| 3 |
Project Incharge/Employees |
Er.K.G. Gupta |
|
| 4 |
Completed Project Information: |
-
Officer Incharge
-
Name of Work
-
Organization Name
-
Stadium
-
Workcode No
-
Approval Year
-
State/District/Place
-
Date of Admin Approval
-
Administrative Approval Amount
-
Estimated Cost
-
Date of Preparation of Estimate
-
Modes of Tender
-
Etendering
-
Technical bid As Per bidding Document
-
Actual Technical Bid Date
-
Financial bid As Per bidding Document
-
Actual Financial Bid Date
-
No of Tenders
-
No. of disqualified Bids at Technical
-
No. of Financial Bids Opened
-
Quote of L1 Bidder
-
Justify Amount
-
Date of Preparation of Justification
-
Awarded Contract
-
Agreement Date
-
Letter of Intent No
-
Letter of Intent Date
-
Work Order No
-
Agreement No
-
Vendor/Executor Name
-
Date of Start As Per Agreement
-
Actual Date of Start
-
Date of Completion As Per Agreement
-
Actual Date of Completion
-
Stipulate Agreement Time
-
Physical Progress of Work in Percentage
-
Financial Progress of Work in Percentage
-
Manual Adopted
-
Tender Complaint
-
No. of Consultants
-
Name of Consultant
|
41 Fields are Filled |
| 5 |
Incomplete Project Information- |
-
Major Department
-
Project Category
-
Contractor
-
Contractor Name
-
Open Tender
-
Prequalification As per bidding document
-
Actual Prequalification Bid Date
-
No. of disqualified Bids at Prequalification
-
Work Order Date
-
Payment Made Till Date
-
No. of Complaint/s
|
11 Fields are Empty |
| 6 |
This project is completed/not completed in time. |
Agrrement Date of Completion-15-04-2010 Actual Date of Completion-31-08-2010 |
Not completed on time |
| 7 |
The project exceeds the budget allocation |
|
|
|
a. at estimate stage in % |
Estimated Cost:254226265 |
|
|
b. at award stage in % |
Awarded Cost:295937892 |
|
|
c. at completion stage in % |
Payment Amount:286982440.00 |
|
| 8 |
Tender Processing |
|
|
|
a. Delay in opening of tender |
As Per Agreement
As Per Actual
|
|
|
i)Pre-qualification stage |
00-00-0000
00-00-0000
|
Data Insufficient |
|
ii)Technical Stage |
12-11-2009
12-11-2009
|
Data Insufficient |
|
iii) Commercial Stage |
16-11-2009
16-11-2009
|
No Delay
|
|
b. Very long time taken for the finalization of tender. |
Date Of Preparation of Justify Amount:17-11-2009
Letter Of Intent Date:17-11-2009
|
Delayed by 17 days
|
|
c. Work awarded on nomination basis. |
OpenTender |
|
|
d. Participation of bidder is too low. |
4 |
|
|
e. Work awarded at higher rates in respect to estimated cost.
|
Awarded Cost-295937892 Estimated Cost-254226265 |
Yes |
| 9 |
Execution Stage
|
|
|
|
a. The work was started late. |
Agreement Date of Start-16-12-2009 Actual Date of Start-16-12-2009 |
No Delay
|
|
b. Time taken for completion of work is beyond the stipulated date of completion. |
Actual Date of Start: 16-12-2009Actual Date of Completion: 31-08-2010
Stipulated Completion Time As Per Agreement: 120
|
258 days
|
|
c. The cost of extra/Deduction/ additional items are more in %. |
Nil |
|
| 10 |
Payments |
|
|
|
a. The physical progress is not matching with the financial progress. |
Work in Percentage-100 Financial Progress Work Percentage-100 |
Matching |
|
b. Delay in making payments
|
Actual Date of Completion-31-08-2010Progress of Work-12-06-2011 |
Delayed by 285 Days |