| Initial Scrunity Report/Observations of Project - Organizing Committee CWG |
| Sl.No |
Information Name |
Informations |
System Remarks |
| 1 |
Name of the Project/Work: |
Cleaning & Waste Management |
|
| 2 |
EXECUTOR/CONTRACTOR/VENDORS: |
Sarvatra Integrated Services |
|
| 3 |
Project Incharge/Employees |
|
Project Incharge/Employees name is Empty |
| 4 |
Completed Project Information: |
-
Name of Work
-
Organization Name
-
Workcode No
-
State/District/Place
-
Administrative Approval Amount
-
No. of Financial Bids Opened
-
Justify Amount
-
Awarded Contract
-
Agreement No
-
Vendor/Executor Name
-
Actual Date of Start
-
Stipulate Agreement Time
-
No. of Consultants
-
Name of Consultant
|
14 Fields are Filled |
| 5 |
Incomplete Project Information- |
-
Major Department
-
Project Category
-
Officer Incharge
-
Stadium
-
Contractor
-
Contractor Name
-
Approval Year
-
Date of Admin Approval
-
Estimated Cost
-
Date of Preparation of Estimate
-
Modes of Tender
-
Open Tender
-
Etendering
-
Prequalification As per bidding document
-
Actual Prequalification Bid Date
-
Technical bid As Per bidding Document
-
Actual Technical Bid Date
-
Financial bid As Per bidding Document
-
Actual Financial Bid Date
-
No of Tenders
-
No. of disqualified Bids at Prequalification
-
No. of disqualified Bids at Technical
-
Quote of L1 Bidder
-
Date of Preparation of Justification
-
Agreement Date
-
Letter of Intent No
-
Letter of Intent Date
-
Work Order No
-
Work Order Date
-
Payment Made Till Date
-
Date of Start As Per Agreement
-
Date of Completion As Per Agreement
-
Actual Date of Completion
-
Physical Progress of Work in Percentage
-
Financial Progress of Work in Percentage
-
Manual Adopted
-
Tender Complaint
-
No. of Complaint/s
|
38 Fields are Empty |
| 6 |
This project is completed/not completed in time. |
Agrrement Date of Completion-00-00-0000 Actual Date of Completion-00-00-0000 |
Data Insufficient |
| 7 |
The project exceeds the budget allocation |
|
|
|
a. at estimate stage in % |
Estimated Cost:0 |
|
|
b. at award stage in % |
Awarded Cost:10203935 |
|
|
c. at completion stage in % |
Payment Amount: |
|
| 8 |
Tender Processing |
|
|
|
a. Delay in opening of tender |
As Per Agreement
As Per Actual
|
|
|
i)Pre-qualification stage |
00-00-0000
00-00-0000
|
Data Insufficient |
|
ii)Technical Stage |
00-00-0000
00-00-0000
|
Data Insufficient |
|
iii) Commercial Stage |
00-00-0000
00-00-0000
|
Data Insufficient |
|
b. Very long time taken for the finalization of tender. |
Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
|
No Delay
|
|
c. Work awarded on nomination basis. |
|
|
|
d. Participation of bidder is too low. |
0 |
|
|
e. Work awarded at higher rates in respect to estimated cost.
|
Awarded Cost-10203935 Estimated Cost-0 |
Data Insufficient |
| 9 |
Execution Stage
|
|
|
|
a. The work was started late. |
Agreement Date of Start-00-00-0000 Actual Date of Start-01-08-2010 |
No Delay
|
|
b. Time taken for completion of work is beyond the stipulated date of completion. |
Actual Date of Start: 01-08-2010Actual Date of Completion: 00-00-0000
Stipulated Completion Time As Per Agreement: 01/08/2010 to 1
|
Data Insufficient |
|
c. The cost of extra/Deduction/ additional items are more in %. |
|
|
| 10 |
Payments |
|
|
|
a. The physical progress is not matching with the financial progress. |
Work in Percentage-0 Financial Progress Work Percentage-0 |
Data Insufficient |
|
b. Delay in making payments
|
Actual Date of Completion-00-00-0000Progress of Work-00-00-0000 |
Data Insufficient |