Initial Scrunity Report/Observations of Project   - CENTRAL PUBLIC WORKS DEPARTMENT
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: Upgradation & renovation of Dr. SPM Swimming Pool Complex for CWG 2010 at Talkatora New Delhi. (SH: Providing UPS System for Sports Lighting).
2 EXECUTOR/CONTRACTOR/VENDORS: M/s. Power House
3 Project Incharge/Employees Sh. V.K. Dhiman
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Stadium
  5. Workcode No
  6. State/District/Place
  7. Date of Admin Approval
  8. Administrative Approval Amount
  9. Estimated Cost
  10. Date of Preparation of Estimate
  11. Modes of Tender
  12. Etendering
  13. Technical bid As Per bidding Document
  14. Actual Technical Bid Date
  15. Financial bid As Per bidding Document
  16. Actual Financial Bid Date
  17. No of Tenders
  18. No. of Financial Bids Opened
  19. Quote of L1 Bidder
  20. Justify Amount
  21. Date of Preparation of Justification
  22. Awarded Contract
  23. Agreement Date
  24. Work Order No
  25. Work Order Date
  26. Agreement No
  27. Vendor/Executor Name
  28. Date of Start As Per Agreement
  29. Actual Date of Start
  30. Date of Completion As Per Agreement
  31. Actual Date of Completion
  32. Stipulate Agreement Time
  33. Physical Progress of Work in Percentage
  34. Financial Progress of Work in Percentage
  35. Manual Adopted
  36. Tender Complaint
  37. No. of Consultants
  38. Name of Consultant
38 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Contractor
  4. Contractor Name
  5. Approval Year
  6. Open Tender
  7. Prequalification As per bidding document
  8. Actual Prequalification Bid Date
  9. No. of disqualified Bids at Prequalification
  10. No. of disqualified Bids at Technical
  11. Letter of Intent No
  12. Letter of Intent Date
  13. Payment Made Till Date
  14. No. of Complaint/s
14 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-16-09-2010
Actual Date of Completion-15-09-2010
Completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:30155365
b. at award stage in % Awarded Cost:30583016
c. at completion stage in % Payment Amount:27707014
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           19-06-2010                          19-06-2010 Data Insufficient
iii) Commercial Stage           24-06-2010                          24-06-2010 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:29-06-2010
Letter Of Intent Date:29-06-2010
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 5
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-30583016
Estimated Cost-30155365
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-03-08-2010
Actual Date of Start-03-08-2010
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 03-08-2010
Actual Date of Completion: 15-09-2010
Stipulated Completion Time As Per Agreement: 45
43 days
c. The cost of extra/Deduction/ additional items are more in %.
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-15-09-2010
Progress of Work-01-12-2011
Delayed by 442 Days


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 0 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 0 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0