Initial Scrunity Report/Observations of Project   - CENTRAL PUBLIC WORKS DEPARTMENT
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: SITC of D.G. Sets
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Sudhir Power Projects Pvt. Ltd.
3 Project Incharge/Employees Sunil Yadav, EE(E), CGED-II, CPWD, IGI Stadium, Ne
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Workcode No
  5. State/District/Place
  6. Estimated Cost
  7. Modes of Tender
  8. Etendering
  9. No of Tenders
  10. No. of Financial Bids Opened
  11. Quote of L1 Bidder
  12. Justify Amount
  13. Awarded Contract
  14. Letter of Intent No
  15. Letter of Intent Date
  16. Agreement No
  17. Vendor/Executor Name
  18. Date of Start As Per Agreement
  19. Actual Date of Start
  20. Date of Completion As Per Agreement
  21. Actual Date of Completion
  22. Stipulate Agreement Time
  23. Physical Progress of Work in Percentage
  24. Financial Progress of Work in Percentage
  25. Manual Adopted
  26. Tender Complaint
  27. No. of Consultants
  28. Name of Consultant
28 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Stadium
  4. Contractor
  5. Contractor Name
  6. Approval Year
  7. Date of Admin Approval
  8. Administrative Approval Amount
  9. Date of Preparation of Estimate
  10. Open Tender
  11. Prequalification As per bidding document
  12. Actual Prequalification Bid Date
  13. Technical bid As Per bidding Document
  14. Actual Technical Bid Date
  15. Financial bid As Per bidding Document
  16. Actual Financial Bid Date
  17. No. of disqualified Bids at Prequalification
  18. No. of disqualified Bids at Technical
  19. Date of Preparation of Justification
  20. Agreement Date
  21. Work Order No
  22. Work Order Date
  23. Payment Made Till Date
  24. No. of Complaint/s
24 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-15-10-2010
Actual Date of Completion-15-10-2010
Completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:98663863
b. at award stage in % Awarded Cost:9478980
c. at completion stage in % Payment Amount:123037778
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           00-00-0000                          00-00-0000 Data Insufficient
iii) Commercial Stage           00-00-0000                          00-00-0000 Data Insufficient
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 2
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-9478980
Estimated Cost-98663863
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-17-05-2009
Actual Date of Start-17-05-2009
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 17-05-2009
Actual Date of Completion: 15-10-2010
Stipulated Completion Time As Per Agreement: 180 Days
516 days
c. The cost of extra/Deduction/ additional items are more in %. NIL
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-15-10-2010
Progress of Work-15-10-2010
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 0 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 0 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0