Initial Scrunity Report/Observations of Project  NHAI-00014925 - NATIONAL HIGHWAY AUTHORITY OF INDIA
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: Improvement of existing of 2-lane road and widening to 4-lane divided carriageway, Operation and Maintenance from Km. 63.000 to Km. 120.000 of NH-11 [Bharatpur Mahua section] in the state of Rajasthan on Built, operate and transfer [BOT basis] under NHDP
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Madhucon Agra Jaipur Expressway Ltd
3 Project Incharge/Employees Y B Singh
4 Completed Project Information:
  1. Major Department
  2. Project Category
  3. Officer Incharge
  4. Name of Work
  5. Organization Name
  6. Workcode No
  7. State/District/Place
  8. Date of Admin Approval
  9. Administrative Approval Amount
  10. Estimated Cost
  11. Modes of Tender
  12. Etendering
  13. Technical bid As Per bidding Document
  14. Actual Technical Bid Date
  15. Financial bid As Per bidding Document
  16. Actual Financial Bid Date
  17. No of Tenders
  18. No. of disqualified Bids at Technical
  19. No. of Financial Bids Opened
  20. Quote of L1 Bidder
  21. Awarded Contract
  22. Agreement Date
  23. Letter of Intent No
  24. Letter of Intent Date
  25. Work Order Date
  26. Agreement No
  27. Vendor/Executor Name
  28. Date of Start As Per Agreement
  29. Actual Date of Start
  30. Date of Completion As Per Agreement
  31. Actual Date of Completion
  32. Stipulate Agreement Time
  33. Physical Progress of Work in Percentage
  34. Financial Progress of Work in Percentage
  35. Manual Adopted
  36. Tender Complaint
  37. No. of Consultants
  38. Name of Consultant
38 Fields are Filled
5 Incomplete Project Information-
  1. Stadium
  2. Contractor
  3. Contractor Name
  4. Approval Year
  5. Date of Preparation of Estimate
  6. Open Tender
  7. Prequalification As per bidding document
  8. Actual Prequalification Bid Date
  9. No. of disqualified Bids at Prequalification
  10. Justify Amount
  11. Date of Preparation of Justification
  12. Work Order No
  13. Payment Made Till Date
  14. No. of Complaint/s
14 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-09-10-2008
Actual Date of Completion-08-05-2009
Not completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:2500000000
b. at award stage in % Awarded Cost:619220000
c. at completion stage in % Payment Amount:
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           04-03-2004                          04-03-2004 Data Insufficient
iii) Commercial Stage           04-03-2004                          04-03-2004 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 3
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-619220000
Estimated Cost-2500000000
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-10-04-2006
Actual Date of Start-10-04-2006
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 10-04-2006
Actual Date of Completion: 08-05-2009
Stipulated Completion Time As Per Agreement: 910
1124 days
c. The cost of extra/Deduction/ additional items are more in %.
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-08-05-2009
Progress of Work-00-00-0000
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 27 0
Scan - Milestones 0 0
Scan - Tender 1 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 1 1
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0