| Initial Scrunity Report/Observations of Project - MUNCIPAL CORPORATION OF DELHI |
| Sl.No |
Information Name |
Informations |
System Remarks |
| 1 |
Name of the Project/Work: |
Covering of Sunahari Nallah from Lala Lajpat Rai Marg (Behind Lodhi Hotel) to Dayal Singh College along Lodhi Road and covering of Kushak Nallah from Jawaharlal Nehru Stadium (South Gate) to IVth Avenue Road, Lodhi Colony, for providing Parking facility f |
|
| 2 |
EXECUTOR/CONTRACTOR/VENDORS: |
M/s Punj Lloyd Ltd. |
|
| 3 |
Project Incharge/Employees |
Ex. Engineer(Special Project), Central Zone |
|
| 4 |
Completed Project Information: |
-
Officer Incharge
-
Name of Work
-
Organization Name
-
Workcode No
-
State/District/Place
-
Date of Admin Approval
-
Administrative Approval Amount
-
Estimated Cost
-
Date of Preparation of Estimate
-
Modes of Tender
-
Etendering
-
Actual Prequalification Bid Date
-
Actual Technical Bid Date
-
Actual Financial Bid Date
-
No of Tenders
-
No. of disqualified Bids at Prequalification
-
No. of Financial Bids Opened
-
Justify Amount
-
Date of Preparation of Justification
-
Awarded Contract
-
Agreement Date
-
Letter of Intent No
-
Letter of Intent Date
-
Work Order No
-
Work Order Date
-
Agreement No
-
Vendor/Executor Name
-
Date of Start As Per Agreement
-
Actual Date of Start
-
Date of Completion As Per Agreement
-
Actual Date of Completion
-
Stipulate Agreement Time
-
Physical Progress of Work in Percentage
-
Financial Progress of Work in Percentage
-
Manual Adopted
-
Tender Complaint
-
No. of Consultants
-
Name of Consultant
|
38 Fields are Filled |
| 5 |
Incomplete Project Information- |
-
Major Department
-
Project Category
-
Stadium
-
Contractor
-
Contractor Name
-
Approval Year
-
Open Tender
-
Prequalification As per bidding document
-
Technical bid As Per bidding Document
-
Financial bid As Per bidding Document
-
No. of disqualified Bids at Technical
-
Quote of L1 Bidder
-
Payment Made Till Date
-
No. of Complaint/s
|
14 Fields are Empty |
| 6 |
This project is completed/not completed in time. |
Agrrement Date of Completion-11-05-2010 Actual Date of Completion-31-08-2010 |
Not completed on time |
| 7 |
The project exceeds the budget allocation |
|
|
|
a. at estimate stage in % |
Estimated Cost:3255000000 |
|
|
b. at award stage in % |
Awarded Cost:3039500000 |
|
|
c. at completion stage in % |
Payment Amount:2929164350 |
|
| 8 |
Tender Processing |
|
|
|
a. Delay in opening of tender |
As Per Agreement
As Per Actual
|
|
|
i)Pre-qualification stage |
00-00-0000
08-09-2008
|
Data Insufficient |
|
ii)Technical Stage |
00-00-0000
10-11-2008
|
Data Insufficient |
|
iii) Commercial Stage |
00-00-0000
27-11-2008
|
Data Insufficient |
|
b. Very long time taken for the finalization of tender. |
Date Of Preparation of Justify Amount:13-12-2008
Letter Of Intent Date:13-12-2008
|
Delayed by 6 days
|
|
c. Work awarded on nomination basis. |
OpenTender |
|
|
d. Participation of bidder is too low. |
4 |
|
|
e. Work awarded at higher rates in respect to estimated cost.
|
Awarded Cost-3039500000 Estimated Cost-3255000000 |
Yes |
| 9 |
Execution Stage
|
|
|
|
a. The work was started late. |
Agreement Date of Start-12-01-2009 Actual Date of Start-12-01-2009 |
No Delay
|
|
b. Time taken for completion of work is beyond the stipulated date of completion. |
Actual Date of Start: 12-01-2009Actual Date of Completion: 31-08-2010
Stipulated Completion Time As Per Agreement: 485
|
596 days
|
|
c. The cost of extra/Deduction/ additional items are more in %. |
|
|
| 10 |
Payments |
|
|
|
a. The physical progress is not matching with the financial progress. |
Work in Percentage-100 Financial Progress Work Percentage-98 |
Not Matching |
|
b. Delay in making payments
|
Actual Date of Completion-31-08-2010Progress of Work-01-08-2011 |
Delayed by 335 Days |