Initial Scrunity Report/Observations of Project   - DELHI DEVELOPMENT AUTHORITY,
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: C/o Indoor Stadium for Table Tennis for Common Wealth Games -2010 at YSC.SH: SITC of substation equipments.
2 EXECUTOR/CONTRACTOR/VENDORS: M/s S.L. Enterprises
3 Project Incharge/Employees Sh. D.K. Jha ,EE(E)
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Stadium
  5. Workcode No
  6. Approval Year
  7. State/District/Place
  8. Date of Admin Approval
  9. Administrative Approval Amount
  10. Estimated Cost
  11. Date of Preparation of Estimate
  12. Modes of Tender
  13. Etendering
  14. Prequalification As per bidding document
  15. Actual Prequalification Bid Date
  16. Technical bid As Per bidding Document
  17. Actual Technical Bid Date
  18. No of Tenders
  19. No. of Financial Bids Opened
  20. Quote of L1 Bidder
  21. Justify Amount
  22. Date of Preparation of Justification
  23. Awarded Contract
  24. Agreement Date
  25. Letter of Intent No
  26. Letter of Intent Date
  27. Work Order No
  28. Agreement No
  29. Vendor/Executor Name
  30. Date of Start As Per Agreement
  31. Actual Date of Start
  32. Date of Completion As Per Agreement
  33. Actual Date of Completion
  34. Stipulate Agreement Time
  35. Physical Progress of Work in Percentage
  36. Financial Progress of Work in Percentage
  37. Manual Adopted
  38. Tender Complaint
  39. No. of Consultants
  40. Name of Consultant
40 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Contractor
  4. Contractor Name
  5. Open Tender
  6. Financial bid As Per bidding Document
  7. Actual Financial Bid Date
  8. No. of disqualified Bids at Prequalification
  9. No. of disqualified Bids at Technical
  10. Work Order Date
  11. Payment Made Till Date
  12. No. of Complaint/s
12 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-03-03-2010
Actual Date of Completion-23-06-2010
Not completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:45535126
b. at award stage in % Awarded Cost:45127393
c. at completion stage in % Payment Amount:
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           14-10-2008                          14-10-2008 Data Insufficient
ii)Technical Stage           17-10-2008                          17-10-2008 Data Insufficient
iii) Commercial Stage           00-00-0000                          00-00-0000 Data Insufficient
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:22-11-2008
Letter Of Intent Date:22-11-2008
Delayed by 70 days
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 3
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-45127393
Estimated Cost-45535126
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-04-03-2009
Actual Date of Start-04-03-2009
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 04-03-2009
Actual Date of Completion: 23-06-2010
Stipulated Completion Time As Per Agreement: 12 months
476 days
c. The cost of extra/Deduction/ additional items are more in %.
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-23-06-2010
Progress of Work-00-00-0000
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 0 0
Scan - Stake Holder Info 1 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 7 4
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0