Initial Scrunity Report/Observations of Project   - CENTRAL PUBLIC WORKS DEPARTMENT
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: Up-gradation Renovation & New Construction in J.N. Stadium Complex New Delhi for Commonwealth Games?2010. (SH: Construction of Temporary Structures (Portable Cabin Type) including internal EI Air Conditioning Toilets water supply/Sanitary fittings an
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Deepali Designs & Exhibits Pvt. Ltd. 9 1st flo
3 Project Incharge/Employees Shri Dineshwar Gaur
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Stadium
  5. Workcode No
  6. State/District/Place
  7. Date of Admin Approval
  8. Administrative Approval Amount
  9. Estimated Cost
  10. Modes of Tender
  11. Etendering
  12. Prequalification As per bidding document
  13. Financial bid As Per bidding Document
  14. Actual Financial Bid Date
  15. No of Tenders
  16. No. of disqualified Bids at Prequalification
  17. No. of Financial Bids Opened
  18. Quote of L1 Bidder
  19. Justify Amount
  20. Awarded Contract
  21. Agreement Date
  22. Letter of Intent No
  23. Letter of Intent Date
  24. Agreement No
  25. Vendor/Executor Name
  26. Date of Start As Per Agreement
  27. Actual Date of Start
  28. Date of Completion As Per Agreement
  29. Actual Date of Completion
  30. Stipulate Agreement Time
  31. Physical Progress of Work in Percentage
  32. Financial Progress of Work in Percentage
  33. Manual Adopted
  34. Tender Complaint
  35. No. of Consultants
  36. Name of Consultant
36 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Contractor
  4. Contractor Name
  5. Approval Year
  6. Date of Preparation of Estimate
  7. Open Tender
  8. Actual Prequalification Bid Date
  9. Technical bid As Per bidding Document
  10. Actual Technical Bid Date
  11. No. of disqualified Bids at Technical
  12. Date of Preparation of Justification
  13. Work Order No
  14. Work Order Date
  15. Payment Made Till Date
  16. No. of Complaint/s
16 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-14-05-2010
Actual Date of Completion-15-09-2010
Not completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:110728344
b. at award stage in % Awarded Cost:107651625
c. at completion stage in % Payment Amount:
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           30-01-2009                          00-00-0000 Data Insufficient
ii)Technical Stage           00-00-0000                          00-00-0000 Data Insufficient
iii) Commercial Stage           25-01-2010                          25-01-2010 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 6
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-107651625
Estimated Cost-110728344
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-15-02-2010
Actual Date of Start-15-02-2010
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 15-02-2010
Actual Date of Completion: 15-09-2010
Stipulated Completion Time As Per Agreement: 90
212 days
c. The cost of extra/Deduction/ additional items are more in %. Nil
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-15-09-2010
Progress of Work-00-00-0000
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 2 0
Scan - Milestones 0 0
Scan - Tender 2 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 0 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0