Initial Scrunity Report/Observations of Project   - ELECTRONICS CORPN OF INDIA LTD
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: supply of Tyre killer,Wedge Barrier and Road Blocker
2 EXECUTOR/CONTRACTOR/VENDORS: Gunnebo Wego GMbH
3 Project Incharge/Employees B mahaveera
4 Completed Project Information:
  1. Project Category
  2. Officer Incharge
  3. Name of Work
  4. Organization Name
  5. Workcode No
  6. Contractor
  7. Approval Year
  8. State/District/Place
  9. Date of Admin Approval
  10. Administrative Approval Amount
  11. Estimated Cost
  12. Date of Preparation of Estimate
  13. Modes of Tender
  14. Etendering
  15. Technical bid As Per bidding Document
  16. Actual Technical Bid Date
  17. Financial bid As Per bidding Document
  18. Actual Financial Bid Date
  19. No of Tenders
  20. No. of disqualified Bids at Technical
  21. No. of Financial Bids Opened
  22. Quote of L1 Bidder
  23. Awarded Contract
  24. Work Order No
  25. Work Order Date
  26. Vendor/Executor Name
  27. Date of Start As Per Agreement
  28. Actual Date of Start
  29. Date of Completion As Per Agreement
  30. Actual Date of Completion
  31. Stipulate Agreement Time
  32. Physical Progress of Work in Percentage
  33. Financial Progress of Work in Percentage
  34. Tender Complaint
34 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Stadium
  3. Contractor Name
  4. Open Tender
  5. Prequalification As per bidding document
  6. Actual Prequalification Bid Date
  7. No. of disqualified Bids at Prequalification
  8. Justify Amount
  9. Date of Preparation of Justification
  10. Agreement Date
  11. Letter of Intent No
  12. Letter of Intent Date
  13. Agreement No
  14. Payment Made Till Date
  15. Manual Adopted
  16. No. of Complaint/s
  17. No. of Consultants
  18. Name of Consultant
18 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-28-02-2010
Actual Date of Completion-28-02-2010
Completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:183084000
b. at award stage in % Awarded Cost:167389000
c. at completion stage in % Payment Amount:
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           00-00-0000                          00-00-0000 Data Insufficient
ii)Technical Stage           07-10-2009                          07-10-2009 Data Insufficient
iii) Commercial Stage           27-10-2009                          27-10-2009 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:00-00-0000
Letter Of Intent Date:00-00-0000
No Delay
c. Work awarded on nomination basis. Limited Tender
d. Participation of bidder is too low. 3
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-167389000
Estimated Cost-183084000
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-31-01-2010
Actual Date of Start-31-01-2010
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 31-01-2010
Actual Date of Completion: 28-02-2010
Stipulated Completion Time As Per Agreement: 29
28 days
c. The cost of extra/Deduction/ additional items are more in %.
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-28-02-2010
Progress of Work-00-00-0000
Data Insufficient


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 2 0
Scan - Milestones 0 0
Scan - Tender 0 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 2 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0