Initial Scrunity Report/Observations of Project   - CENTRAL PUBLIC WORKS DEPARTMENT
Sl.No Information Name Informations System Remarks
1 Name of the Project/Work: Remodelling & upgradation of MDC National Stadium for Commonwealth Games - 2010. (SH: SITC of LED Scoreboard)
2 EXECUTOR/CONTRACTOR/VENDORS: M/s Catvision Products Ltd.
3 Project Incharge/Employees Er. N.S. Rawat
4 Completed Project Information:
  1. Officer Incharge
  2. Name of Work
  3. Organization Name
  4. Stadium
  5. Workcode No
  6. State/District/Place
  7. Date of Admin Approval
  8. Administrative Approval Amount
  9. Estimated Cost
  10. Date of Preparation of Estimate
  11. Modes of Tender
  12. Etendering
  13. Prequalification As per bidding document
  14. Actual Prequalification Bid Date
  15. Technical bid As Per bidding Document
  16. Actual Technical Bid Date
  17. Financial bid As Per bidding Document
  18. Actual Financial Bid Date
  19. No of Tenders
  20. No. of disqualified Bids at Prequalification
  21. No. of Financial Bids Opened
  22. Quote of L1 Bidder
  23. Justify Amount
  24. Date of Preparation of Justification
  25. Awarded Contract
  26. Agreement Date
  27. Letter of Intent No
  28. Letter of Intent Date
  29. Agreement No
  30. Vendor/Executor Name
  31. Date of Start As Per Agreement
  32. Actual Date of Start
  33. Date of Completion As Per Agreement
  34. Actual Date of Completion
  35. Stipulate Agreement Time
  36. Physical Progress of Work in Percentage
  37. Financial Progress of Work in Percentage
  38. Manual Adopted
  39. Tender Complaint
  40. No. of Complaint/s
  41. No. of Consultants
  42. Name of Consultant
42 Fields are Filled
5 Incomplete Project Information-
  1. Major Department
  2. Project Category
  3. Contractor
  4. Contractor Name
  5. Approval Year
  6. Open Tender
  7. No. of disqualified Bids at Technical
  8. Work Order No
  9. Work Order Date
  10. Payment Made Till Date
10 Fields are Empty
6 This project is completed/not completed in time. Agrrement Date of Completion-31-01-2010
Actual Date of Completion-26-02-2010
Not completed on time
7 The project exceeds the budget allocation
a. at estimate stage in % Estimated Cost:24554996
b. at award stage in % Awarded Cost:27737554
c. at completion stage in % Payment Amount:25937164
8 Tender Processing
a. Delay in opening of tender       As Per Agreement              As Per Actual
i)Pre-qualification stage           10-11-2009                          19-11-2009 Delayed by 9 days No Delay
ii)Technical Stage           03-12-2009                          03-12-2009 Data Insufficient
iii) Commercial Stage           10-12-2009                          10-12-2009 No Delay
b. Very long time taken for the finalization of tender. Date Of Preparation of Justify Amount:11-12-2009
Letter Of Intent Date:11-12-2009
No Delay
c. Work awarded on nomination basis. OpenTender
d. Participation of bidder is too low. 8
e. Work awarded at higher rates in respect to estimated cost.
Awarded Cost-27737554
Estimated Cost-24554996
Yes
9 Execution Stage
a. The work was started late.
Agreement Date of Start-18-12-2009
Actual Date of Start-18-12-2009
No Delay
b. Time taken for completion of work is beyond the stipulated date of completion. Actual Date of Start: 18-12-2009
Actual Date of Completion: 26-02-2010
Stipulated Completion Time As Per Agreement: 45 Days
70 days
c. The cost of extra/Deduction/ additional items are more in %. Nil
10 Payments
a. The physical progress is not matching with the financial progress. Work in Percentage-100
Financial Progress Work Percentage-100
Matching
b. Delay in making payments
Actual Date of Completion-26-02-2010
Progress of Work-31-12-2010
Delayed by 308 Days


Uploaded Documents

Document Name Uploaded Data Entered
Scan - Work Order 0 0
Scan - Milestones 0 0
Scan - Tender 1 0
Scan - Stake Holder Info 0 0
Scan - Events 0 0
Scan - Cost Details 0 0
Scan - Deviations 0 0
Scan - Bills 0 0
Media Scan 0 0
Scan - Budget 0 0
Photos 0 0