Work Code Number : 000-09-N-J-N-D-FO-168
Name of the Project : Construction of Retaining wall using RCC Pre-cast box of size 3.0x3.0x1.0mtrs in V.Valley on left side fromCH:8.90 to 9.00 Km with road in Vrishabavathi Valley.
Estimated Cost : 29500000 Approved Cost : 29500000
Expenditure Incurred : 0 Approved Cost in Percentage : 0
Zone : Head Office Chief Engineer : CE SWD-2
Division : Executive Engineer : Shivakumar S
Sub Division : Assistant Executive Engineer : G N Sadananda
Ward Name : Assistant Engineer : Anuradha S Kankanavad
Contractor Class : Class 1 A (Civil) Contractor Name :