Workcode & Project Details
Work Code Number
: 203-09-N-J-N-D-FO-016
Name of the Project
: Construction of Box drain & Protective works at Ch.250.00m to ch.325.00m of SWD From Arunodaya Vidya Samsthe to Herohalli tank in Mahadeshwara Nagara
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 8500000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 0
Work Order Date
: 18-05-2009
Expenditure Incurred
: 4995000
Client Name
:
Approved Cost in Percentage
: 0
Location Details
District
:
Constituency
: Yeshwanthpura
Zone
: Head Office
Department Type
:
Division
:
Sub Division
:
Ward Name
:
Ward No
:
Locality
:
Postal Code
:
Area
: Mahadeshwara nagara
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2008-09
Budget Category(Head of Account)
: SWD 2008-09
Scheme
: JNNURM
Amount Alloted
:
Administrative Approval No and Date
: 1331/2008-09 00-00-0000
Technical Sanction No and Date
: CE/SWD/Tech/13/09-10 00-00-0000
Technical Notification No and Date
: 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: CE SWD-1
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: B.S.Sudarshan
Designation
: Executive Engineer
User ID
: 24104
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Puttasheshagiri & Mahanthesh
Designation
: AEE
User ID
: 2010401
Mobile Number
:
Email Id
:
Ward Engineer
Name
: V.Shreenath
Designation
: Assistant Engineer
User ID
: 241040102
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Mohan.S.L
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 19-12-2008
Probable Date of completion
:26-02-2010
Scheduled date of completin as per contract
: 17-11-2009
Actual Date of Completion
: 00-00-0000
Work Status
: Completed
Spill Over / Programme of Work and Year
: Programme of Work
Percentage of Physical Progress
: 0
Remarks
: RCC Box Culverts & U shape drain of 119.00m completed,
Category Details
Category
:
Type of Work
:
Sub Work
: