logo
Workcode & Project Details
Work Code Number : 026-08-N-G-L-B-FO-001
Name of the Project : CONSTRUCTION OF AMBEDKAR BHAVAN AT SITE NO-68 JAKKARAYANAKERE W-26
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2146000
Workcode Approval Date : 00-00-0000 Approved Cost : 2146000
Work Order Date : 24-07-2008 Expenditure Incurred : 1565000
Client Name : Approved Cost in Percentage : 19
Location Details
District : Constituency : Gandhi Nagar
Zone : West Department Type :
Division : Gandhi Nagar Sub Division : Gandhi Nagar
Ward Name : Okalipuram Ward No : 96
Locality : Postal Code :
Area : JAKKARAYANAKERE
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) :
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : SE(MPED)PR/32/7-8  00-00-0000
Technical Sanction No and Date : SE(MPED)PR/22/7-8  00-00-0000
Technical Notification No and Date : EE/P-W/MPED/TEND/GL/7/8-9  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : V.S.PADMANBHACHAR
Designation : Executive Engineer
User ID : 32104
Mobile Number :
Email Id :
Sub-Division Engineer
Name : L.VENKATESH
Designation : AEE
User ID : 3210403
Mobile Number :
Email Id :
Ward Engineer
Name : H.J.SHIVASHANKAR MURTHY
Designation : Assistant Engineer
User ID : 321040002
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :18-04-2008
Commencement Date : 00-00-0000 Probable Date of completion :07-11-2008
Scheduled date of completin as per contract : 23-11-2008 Actual Date of Completion : 07-11-2008
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 20-05-2024 14:39:38