logo
Workcode & Project Details
Work Code Number : 026-09-N-S-E-R-PC-002 003
Name of the Project : Prov CC paving & sanitary facilities to houses in Jakkarayanakere & Hanumanthappa colony block in W-26.
Short Name of Project :Prov CC paving & sanitary facilities to houses
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 3000000
Workcode Approval Date : 00-00-0000 Approved Cost : 3000000
Work Order Date : 28-02-2009 Expenditure Incurred : 3295000
Client Name : Approved Cost in Percentage : 9.98
Location Details
District : Constituency : Gandhi Nagar
Zone : West Department Type :
Division : Gandhi Nagar Sub Division : Gandhi Nagar
Ward Name : Subhash Nagar Ward No : 95
Locality : Postal Code :
Area : Jakkarayanakere & Hanumanthappa Colony
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : GOK Grant 2008-09
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : JC/218/08-2009  31-12-2008
Technical Sanction No and Date : CE/150/08-2009  26-12-2008
Technical Notification No and Date : EE(GN)/TEND/GL-05/08-09  10-10-2008
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : R.Idayavendan
Designation : Executive Engineer
User ID : 32102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Prabhakar
Designation : AEE
User ID : 3210201
Mobile Number :
Email Id :
Ward Engineer
Name : Shivamallu
Designation : Assistant Engineer
User ID : 321020103
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :07-04-2009
Commencement Date : 10-04-2009 Probable Date of completion :07-06-2009
Scheduled date of completin as per contract : 30-04-2009 Actual Date of Completion : 07-06-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 19-05-2024 23:33:46