Work Code Number : 027-09-N-G-K-B-FO-001
Name of the Project : providinf and Construction of temporary market shed at Sheshadripuram market in ward No. 27
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 277000
Workcode Approval Date : 00-00-0000 Approved Cost : 304000
Work Order Date : 18-05-2009 Expenditure Incurred : 301000
Client Name : Approved Cost in Percentage : 3.04
Location Details
District : Constituency : Gandhi Nagar
Zone : West Department Type :
Division : Gandhi Nagar Sub Division : Gandhi Nagar
Ward Name : Gandhi Nagar Ward No : 94
Locality : Postal Code :
Area : Sheshadripuram vegetable market
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) :
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : EE/P-W/ADMN/37/08-09.  00-00-0000
Technical Sanction No and Date : EE/PW/TS/37/08-09.  00-00-0000
Technical Notification No and Date : BBMP/EE/PW/TEND/GL-22/08-09.  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : sri. V.S. Padmanabhachar
Designation : Executive Engineer
User ID : 32104
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri. L. Venkatesh
Designation : AEE
User ID : 3210403
Mobile Number :
Email Id :
Ward Engineer
Name : Sri. L. A. Udaya Shankar
Designation : Assistant Engineer
User ID : 321040001
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :05-06-2009
Commencement Date : 00-00-0000 Probable Date of completion :17-08-2009
Scheduled date of completin as per contract : 17-08-2009 Actual Date of Completion : 29-06-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : work completed.