logo
Workcode & Project Details
Work Code Number : 204-08-I-S-E-R-AS-019
Name of the Project : Providing RCC drain and Asphalting road from KAIDB main road to Kundalahally to Sai Mandhira in Mahadevapura Sub-division
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 8728000
Workcode Approval Date : 00-00-0000 Approved Cost : 8728000
Work Order Date : 23-11-2007 Expenditure Incurred : 8728000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Mahadevapura
Zone : Mahadevapura Department Type :
Division : Mahadevapura Sub Division : Hoodi
Ward Name : Doddanekkundi Ward No : 85
Locality : Postal Code :
Area : KAIDB main road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Special Development grants P.1741
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date :   00-00-0000
Technical Sanction No and Date : 36/07-08  00-00-0000
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(MAHADEVAPURA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Basavaraje Gowda
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : G.Mallikarjun
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Shankar Bharathi
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 23-11-2007 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 23-05-2008 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 17-05-2024 13:23:56