logo
Workcode & Project Details
Work Code Number : 204-09-N-G-V-U-PI-007
Name of the Project : Providing and laying GI pipe to Mini tank parallel to the railway line in Kaverinagara in Mahadevapura Sub-division
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 75000
Workcode Approval Date : 00-00-0000 Approved Cost : 75000
Work Order Date : 30-06-2008 Expenditure Incurred : 75000
Client Name : Approved Cost in Percentage : 0.75
Location Details
District : Constituency : Mahadevapura
Zone : Mahadevapura Department Type :
Division : Mahadevapura Sub Division : Hoodi
Ward Name : Doddanekkundi Ward No : 85
Locality : Postal Code :
Area : Kaverinagara
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Water Supply P.1802 new zones
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 18/2008-09  00-00-0000
Technical Sanction No and Date : 18/2008-09  00-00-0000
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(MAHADEVAPURA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE.(Mahadevapura)
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : AEE.(Hudi)
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : AE.(doddanekkundi)
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 30-06-2008 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 07-07-2008 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 17-05-2024 12:48:39