Workcode & Project Details
Work Code Number
: 073-10-N-G-T-S-LG-001
Name of the Project
: Providing High Masts at Old Airport Area
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 900000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 900000
Work Order Date
: 28-10-2009
Expenditure Incurred
: 640000
Client Name
:
Approved Cost in Percentage
: 640150
Location Details
District
:
Constituency
: K.R.Puram
Zone
: Mahadevapura
Department Type
:
Division
: K.R.Puram
Sub Division
: HALAirport
Ward Name
: HAL Airport
Ward No
: 87
Locality
:
Postal Code
:
Area
: Old Airport Area
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: Pwd (Electrical) SR 2007-08
Budget Category(Head of Account)
: High Mast at Circles
Scheme
: No Scheme
Amount Alloted
:
Administrative Approval No and Date
: AS/EE/ELE/EAST/41/2009-10 00-00-0000
Technical Sanction No and Date
: TS/EE/ELE/EAST/43/09-10 00-00-0000
Technical Notification No and Date
: No. EE/Ele/East/TN/GL/12/2008-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E(MAHADEVAPURA)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Sri. B.N.Subbareddy
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Sri R. Radhakrishna
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: Sri P.Jnaneshwar
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Electrical)
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 00-00-0000
Probable Date of completion
:30-06-2010
Scheduled date of completin as per contract
: 14-12-2009
Actual Date of Completion
: 00-00-0000
Work Status
: Work In Progress
Spill Over / Programme of Work and Year
: Programme of Work
Percentage of Physical Progress
: 0
Remarks
:
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 19-05-2024 21:01:40