Work Code Number : 043-10-N-G-E-R-IM-001
Name of the Project : Footh path improvements to white field road from K.R.Puram hanging Bridge to hope parm junction via hoodi junction(820 to 1630.00mtr)
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 5413000
Workcode Approval Date : 00-00-0000 Approved Cost : 5000000
Work Order Date : 14-10-2009 Expenditure Incurred : 5413000
Client Name : Approved Cost in Percentage : 50
Location Details
District : Constituency : K.R.Puram
Zone : Mahadevapura Department Type :
Division : K.R.Puram Sub Division : HoraMavu
Ward Name : Vijinapura Ward No : 51
Locality : Postal Code :
Area : ITPL Road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : P-87additional grants
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 100/09-10  00-00-0000
Technical Sanction No and Date : 209/09-10  00-00-0000
Technical Notification No and Date : EE/KRP/21/2009-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(MAHADEVAPURA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : M.Venugopal
Designation : Executive Engineer
User ID : 38101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : R.Rajagopalareddy
Designation : AEE
User ID : 3810101
Mobile Number :
Email Id :
Ward Engineer
Name : Jayaprakash.B
Designation : Assistant Engineer
User ID : 381010102
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :15-10-2009
Commencement Date : 15-10-2009 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 14-01-2010 Actual Date of Completion : 30-03-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :