logo
Workcode & Project Details
Work Code Number : 044-10-N-G-E-R-AS-001
Name of the Project : Asphalting to roads in Shanthi Layout M.V.Nagara 2nd Block Akshaya Nagara 2nd Block and Manjunatha Layout in R.M.Nagara ward area
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 9900000
Workcode Approval Date : 00-00-0000 Approved Cost : 10651000
Work Order Date : 28-10-2009 Expenditure Incurred : 10645000
Client Name : Approved Cost in Percentage : 106.51
Location Details
District : Constituency : K.R.Puram
Zone : Mahadevapura Department Type :
Division : K.R.Puram Sub Division : HoraMavu
Ward Name : Ramamurthy Nagar Ward No : 26
Locality : Postal Code :
Area : Shanthi Layout Akshaya Nagara 2nd Block and Manjunatha Layout
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : Additional grants
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date :   00-00-0000
Technical Sanction No and Date : page-42 48/09-10  00-00-0000
Technical Notification No and Date : 22/24/8/2009  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(MAHADEVAPURA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Venugopala
Designation : Executive Engineer
User ID : 38101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Raja Gopalareddy
Designation : AEE
User ID : 3810101
Mobile Number :
Email Id :
Ward Engineer
Name : srinivasa.P.N
Designation : Assistant Engineer
User ID : 381010103
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Ganesh.T
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :28-10-2009
Commencement Date : 28-10-2009 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 28-01-2010 Actual Date of Completion : 28-01-2010
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 18-05-2024 20:22:47