Work Code Number : 021-10-N-W-E-R-CO-012
Name of the Project : Construction of cement concrete roads to main & cross roads from Sondekoppa road upto AK Colony in Nalagadaranahalli Village.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 4980000
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 19-08-2009 Expenditure Incurred : 5303000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Dasarahalli
Zone : Dasarahalli Department Type :
Division : Hegganahalli Sub Division : Peenya Industrial Area
Ward Name : Chokkasandra Ward No : 39
Locality : Postal Code :
Area : Chokkasandra
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : S.R 2008-09
Budget Category(Head of Account) : Grant
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 130/09-10  00-00-0000
Technical Sanction No and Date : 186/09-10  00-00-0000
Technical Notification No and Date : 15  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(DASARAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Keera Naik
Designation : Executive Engineer
User ID : 36102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : P.B.Prakash
Designation : AEE
User ID : 3610201
Mobile Number :
Email Id :
Ward Engineer
Name : Devaraj
Designation : Assistant Engineer
User ID : 361020102
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Mahesh.K.N
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :26-09-2009
Commencement Date : 19-08-2009 Probable Date of completion :19-11-2009
Scheduled date of completin as per contract : 19-11-2009 Actual Date of Completion : 26-09-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Paid