Workcode & Project Details
Work Code Number
: 203-08-I-G-H-P-FE-045
Name of the Project
: Providing chain link fencing and other development works at H.T.line park part-6 in HMT Layout Nelagadaranahalli dasarahalli Zone.
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 0
Workcode Approval Date
: 00-00-0000
Approved Cost
: 1128000
Work Order Date
: 27-08-2009
Expenditure Incurred
: 1125000
Client Name
:
Approved Cost in Percentage
: 8.45
Location Details
District
:
Constituency
: Dasarahalli
Zone
: Dasarahalli
Department Type
:
Division
: Hegganahalli
Sub Division
: Peenya Industrial Area
Ward Name
: Chokkasandra
Ward No
: 39
Locality
:
Postal Code
:
Area
:
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2008-09
Budget Category(Head of Account)
: JANODAYNAVANA
Scheme
: Janodyanavana
Amount Alloted
:
Administrative Approval No and Date
: CE/D/ADMN/72/09-10 08-05-2009
Technical Sanction No and Date
: CE//TS/75/09-10 00-00-0000
Technical Notification No and Date
: 16-07-2009
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E(DASARAHALLI)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: EE.(Hegganahalli)
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: S CHANDERA SHEKER
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: T.Raju
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 B (Civil)
Contractor Name
: Govindaraju.S.D
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 27-08-2009
Probable Date of completion
:26-11-2009
Scheduled date of completin as per contract
: 21-10-2009
Actual Date of Completion
: 26-11-2009
Work Status
: Completed
Spill Over / Programme of Work and Year
:
Percentage of Physical Progress
: 0
Remarks
:
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 28-04-2024 10:25:27