logo
Workcode & Project Details
Work Code Number : 201-08-I-S-E-R-IM-003
Name of the Project : Improvements to Kothanur main road from Chunchagatta to kothanur
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 9526000
Workcode Approval Date : 00-00-0000 Approved Cost : 9526000
Work Order Date : 26-10-2007 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 95.26
Location Details
District : Constituency : Bangalore South
Zone : Bommanahalli Department Type :
Division : Uttarahalli Sub Division : Yalachenahalli
Ward Name : Konanakunte Ward No : 195
Locality : Postal Code :
Area : Chunchaghatta
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2006-07
Budget Category(Head of Account) : Public Works(Zonal)
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : JC(BH)/AS/103/07-08  00-00-0000
Technical Sanction No and Date : SE(BH)/TS/38/07-08  00-00-0000
Technical Notification No and Date : EE(BH)/Tend/05/07-08  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE (BOMMANAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Srikantegowda
Designation : Executive Engineer
User ID : 34106
Mobile Number :
Email Id :
Sub-Division Engineer
Name : N.A Khan
Designation : AEE
User ID : 3410601
Mobile Number :
Email Id :
Ward Engineer
Name : Ramachandra
Designation : Assistant Engineer
User ID : 341060102
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Others Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :11-03-2008
Commencement Date : 26-10-2007 Probable Date of completion :03-11-2008
Scheduled date of completin as per contract : 25-02-2008 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 28-04-2024 06:12:31