Work Code Number : 201-08-N-G-H-B-FO-002
Name of the Project : Providing wathch man Quarters work to the park at Ibbaluru gundutopu in front of Temple(Change of place to RBI Layout4th main4th cross)
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 216000
Workcode Approval Date : 00-00-0000 Approved Cost : 216000
Work Order Date : 29-05-2009 Expenditure Incurred : 216000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Bangalore South
Zone : Bommanahalli Department Type :
Division : Uttarahalli Sub Division : Yalachenahalli
Ward Name : Konanakunte Ward No : 195
Locality : Postal Code :
Area : RBI LAYOUT 4TH MAIN 4TH CROSS.
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JANOODYANA PARKS
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : JC/B/BBMP/AS/30/08-09  00-00-0000
Technical Sanction No and Date : EE/B/TS/04/08-09  00-00-0000
Technical Notification No and Date : HS/B/TEND/68/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE (BOMMANAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE.(Uttarhalli)
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : B.C.ANAND
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : ATHIKUR REHMAN IDRUS
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :02-06-2009
Commencement Date : 00-00-0000 Probable Date of completion :28-08-2009
Scheduled date of completin as per contract : 28-08-2009 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :