Workcode & Project Details
Work Code Number
: 004-12-000020
Name of the Project
: Drilling of Borewells, Providing pump and Motors to borewells in Chikkabommasandra, Someshwara Nagara in ward No:04 of Yelahanka Satellite Town Sub Division.
Short Name of Project
:Drilling of Borewells, Providing pump and Motors to borewells
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 26-06-2013
Estimated Cost
: 1150000
Workcode Approval Date
: 22-05-2012
Approved Cost
: 1179855
Work Order Date
: 10-05-2012
Expenditure Incurred
: 1179855
Client Name
: H.Suresh
Approved Cost in Percentage
: 4.45
Location Details
District
:
Constituency
: Yelahanka
Zone
: Yelahanka
Department Type
:
Division
: Yelahanka
Sub Division
: Yelahanka Satellite Town
Ward Name
: Yelahanka Satellite
Ward No
: 4
Locality
:
Postal Code
: 560064
Area
:
Approval Details
Approved By
: CE/Yelahannka Zone
Year of SR Adopted for Preparation of Estimate
: 2012-13
Budget Category(Head of Account)
:
Scheme
: P1802 Water supply New Areas
Amount Alloted
: Budgeted
Administrative Approval No and Date
: 186/2011/12 08-03-2012
Technical Sanction No and Date
: 169/2011-12 14-03-2012
Technical Notification No and Date
: 10/2011-12 09-03-2012
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: Sri.P.S.Ramesh
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Rangaiah
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: A Srinivas Murthy ( Yelankha Setallite Town)
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: Dharmasingh Chatru Naik
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Suresh.N.L
Work Status Details
Agreement No. & Date
: 3212012-13 10-05-2012
Site Handed Over Date
:10-05-2012
Commencement Date
: 11-05-2012
Probable Date of completion
:10-08-2012
Scheduled date of completin as per contract
: 10-08-2012
Actual Date of Completion
: 10-08-2012
Work Status
: Completed
Spill Over / Programme of Work and Year
:
Percentage of Physical Progress
: 0
Remarks
: 1st and Final Bill
Category Details
Category
: Media and broadcasting
Type of Work
: Media and broadcasting
Sub Work
: Media and broadcasting
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 19-06-2024 03:45:29