Workcode & Project Details
Work Code Number
: 002-11-000057
Name of the Project
: Construction of RCC drain at Kondappa layout Western side in ward No-02 of Yelahanka Sub Division
Short Name of Project
:Construction of RCC drain at Kondappa layout Western side in ward No-02 of Yelahanka Sub Division
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 28-03-2011
Estimated Cost
: 1960000
Workcode Approval Date
: 28-03-2011
Approved Cost
: 2051826
Work Order Date
: 10-10-2011
Expenditure Incurred
: 2051826
Client Name
: N. C Suresh
Approved Cost in Percentage
: 4.7
Location Details
District
:
Constituency
: Yelahanka
Zone
: Yelahanka
Department Type
:
Division
: Yelahanka
Sub Division
: yelahanka
Ward Name
: Chowdeshwari
Ward No
: 2
Locality
:
Postal Code
: 5600064
Area
: kondappa layout westen side
Approval Details
Approved By
: commissioner
Year of SR Adopted for Preparation of Estimate
: 2010-11
Budget Category(Head of Account)
: P0001
Scheme
: Pow
Amount Alloted
: Budgeted
Administrative Approval No and Date
: 47 07-07-2011
Technical Sanction No and Date
: 61 21-07-2011
Technical Notification No and Date
: 6 08-06-2011
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: Sri.P.S.Ramesh
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: EE(Yelahanka)
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: AEE(yelahanka)
Designation
: AEE
User ID
: 0
Mobile Number
: 9480589835
Email Id
: aeeynk12@gmail.com
Ward Engineer
Name
: AE(Chowdeshwari)
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
: 9480683420
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Suresh.A
Work Status Details
Agreement No. & Date
: 10-10-2011 00-00-0000
Site Handed Over Date
:10-10-2011
Commencement Date
: 10-10-2011
Probable Date of completion
:31-12-2011
Scheduled date of completin as per contract
: 10-01-2012
Actual Date of Completion
: 31-12-2011
Work Status
: Completed
Spill Over / Programme of Work and Year
:
Percentage of Physical Progress
: 100
Remarks
: work completed
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 09-06-2024 05:56:51