logo
Workcode & Project Details
Work Code Number : 002-11-000053
Name of the Project : Providing asphlating from Doddaballapura main road to Kenchenahalli in Ward No.2
Short Name of Project :Providing asphlating
Project Code : 002-11-000053 Package Code : 0
Date of Issue of Workcode : 30-04-2011 Estimated Cost : 4900000
Workcode Approval Date : 29-04-2011 Approved Cost : 5390000
Work Order Date : 01-06-2011 Expenditure Incurred : 5390000
Client Name : Technical Manager (West) KRIDL, Bangaluru Approved Cost in Percentage : 10
Location Details
District : Constituency : Yelahanka
Zone : Yelahanka Department Type :
Division : Yelahanka Sub Division : yelahanka
Ward Name : Chowdeshwari Ward No : 2
Locality : Postal Code : 560064
Area : Kenchenahalli in Ward No.2
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2010-11
Budget Category(Head of Account) : P2334
Scheme : Development works Yelahanka assembly Constituency
Amount Alloted : Budgeted
Administrative Approval No and Date : 03/2011-12  23-05-2011
Technical Sanction No and Date : 14/2011-12  24-05-2011
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : Sri.P.S.Ramesh
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE(Yelahanka)
Designation : Executive Engineer
User ID : 0
Mobile Number : 9480683365
Email Id : eeynk2009@gmail.com
Sub-Division Engineer
Name : AEE(yelahanka)
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : AE(Chowdeshwari)
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date : 158/2011-12  01-06-2011 Site Handed Over Date :01-06-2011
Commencement Date : 02-06-2011 Probable Date of completion :01-09-2011
Scheduled date of completin as per contract : 01-09-2011 Actual Date of Completion : 01-09-2011
Work Status : Completed Spill Over / Programme of Work and Year :   
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 17-06-2024 03:27:52