Work Code Number : 002-11-000025
Name of the Project : Providing Permanent Electrical Service and Supplying Generator to Newly constructed BBMP Office building in ward No-2 of Yelahanka Sub Division.
Short Name of Project :Providing Permanent Electrical Service and Supplying Generator
Project Code : Package Code : 0
Date of Issue of Workcode : 16-12-2010 Estimated Cost : 1000000
Workcode Approval Date : 22-11-2010 Approved Cost : 736929
Work Order Date : 18-08-2011 Expenditure Incurred : 736929
Client Name : Lakshmi Varadaraja Electricals stores Approved Cost in Percentage : 0
Location Details
District : Constituency : Yelahanka
Zone : Yelahanka Department Type :
Division : Yelahanka Sub Division : yelahanka
Ward Name : Chowdeshwari Ward No : 2
Locality : Postal Code : 560064
Area : Newly constructed BBMP Office building in ward No-2 of Yelahanka
Approval Details
Approved By : EE
Year of SR Adopted for Preparation of Estimate : 2010-11
Budget Category(Head of Account) : P1771
Scheme : POW Works 2010-11
Amount Alloted : Budgeted
Administrative Approval No and Date : 60/2010-11  19-01-2011
Technical Sanction No and Date : 60/2010-11  19-01-2011
Technical Notification No and Date : 02/2010-11  21-01-2011
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : Sri.P.S.Ramesh
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE(Yelahanka)
Designation : Executive Engineer
User ID : 0
Mobile Number : 9900810636
Email Id : eeynk2009@gmail.com
Sub-Division Engineer
Name : AEE(yelahanka)
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : AE(Chowdeshwari)
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date : 183/2010-11  18-08-2011 Site Handed Over Date :18-08-2011
Commencement Date : 19-08-2011 Probable Date of completion :18-11-2011
Scheduled date of completin as per contract : 18-11-2011 Actual Date of Completion : 18-11-2011
Work Status : Completed Spill Over / Programme of Work and Year :   
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 09-06-2024 01:14:50