Agreement No. & Date : 00-00-0000
|
Site Handed Over Date :06-07-2009
|
Commencement Date : 00-00-0000
|
Probable Date of completion :31-12-2009
|
Scheduled date of completin as per contract : 02-08-2009
|
Actual Date of Completion : 00-00-0000
|
Work Status : Work In Progress
|
Spill Over / Programme of Work and Year : Spill Over
|
Percentage of Physical Progress : 0
|
Remarks : work under progress. work delayed due to sub surface utility services
|