Name of the Project : Construction of Toilet Block at J.P.colony in Maruthingara Sub Division
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 501715
Workcode Approval Date : 00-00-0000 Approved Cost : 501715
Work Order Date : 28-08-2009 Expenditure Incurred : 5216000
Client Name : Approved Cost in Percentage : 501715
Location Details
District : Constituency : Yelahanka
Zone : Yelahanka Department Type :
Division : Yelahanka Sub Division : yelahanka
Ward Name : Chowdeshwari Ward No : 2
Locality : Postal Code :
Area : J.P.Colony
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : pow 2009-10
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 165-2009-10  00-00-0000
Technical Sanction No and Date : 165-2009-10  00-00-0000
Technical Notification No and Date : 17-2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(YALAHANKA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Rangaiah
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Rajanna
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Ramasanjeevaiah
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 3 (Civil) Contractor Name : Shanthraj.K
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :01-09-2009
Commencement Date : 00-00-0000 Probable Date of completion :03-12-2009
Scheduled date of completin as per contract : 03-12-2009 Actual Date of Completion : 01-01-1999
Work Status : Work In Progress Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Change of Place Proposed work in Progress