Name of the Project : Improvements to traffic island in Kogilu circle in ward no:01
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 3200011.6
Workcode Approval Date : 00-00-0000 Approved Cost : 3200011.6
Work Order Date : 20-08-2009 Expenditure Incurred : 320000
Client Name : Approved Cost in Percentage : 320011.6
Location Details
District : Constituency : Yelahanka
Zone : Yelahanka Department Type :
Division : Yelahanka Sub Division : yelahanka
Ward Name : Kempegowda Ward No : 1
Locality : Postal Code :
Area : Kogilu circle in ward no:01
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : SR 2008-09
Budget Category(Head of Account) : POW 2009-10
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 139/2009-10  06-04-2009
Technical Sanction No and Date : 139/2009-10  06-04-2009
Technical Notification No and Date : EE/YNK/T-17/2008-09  28-02-2009
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(YALAHANKA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri.Rangaiah.A.G
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Rajanna
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Devarajaiah
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name : Sathish.R
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :21-08-2009
Commencement Date : 00-00-0000 Probable Date of completion :21-11-2009
Scheduled date of completin as per contract : 21-11-2009 Actual Date of Completion : 21-11-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :